| Original Master Plan Items |
May 1994 Status |
August 1997 Status |
March 1999 Status |
November 2005 Status |
| Brown Chapel (I) |
Completed 1984 |
Completed 1984 |
Completed 1984 |
Completed 1984 |
| Church Facility North (5) |
|
|
|
Completed 2003 |
| Church Facility South (6) |
|
|
|
Completed 2003 |
| Goodwin Chapel |
|
|
|
1999 demolition for church building |
| Flex Housing (III) |
Completed 1991 |
Completed 1991 |
Completed 1991 |
Completed 1991 |
| Finch dorm addition (IV) |
Completed 1989 |
Completed 1989 |
Completed 1989 |
Completed 1989 |
| Wiley dorm addition (V) |
Completed 1989 |
Completed 1989 |
Completed 1989 |
Completed 1989 |
| Ryan Learning Center (VI) |
Completed 1993 |
Completed 1993 |
Completed 1993 |
Completed 1993 |
| Starkey A Remodel |
|
Completed 1997 for Bookstore move to Nichollson Commons |
Completed 1999 for post office and print shop |
Completed 1999 |
| Lotus house moved and remodeled (VIII) |
|
Completed 1995 |
Completed 1995 |
Completed 1995 |
| Tingley house moved (VII) (Communications) |
|
Completed 1994 - renamed Cabrillo Hall |
Completed 1994 - renamed Cabrillo Hall |
Completed 1994 - renamed Cabrillo Hall |
| Cooper Music Building (IX) |
|
Completed 1995 |
Completed 1995 |
Completed 1995 |
| Nicholson Student Commons (11) |
|
|
Completed 1997 |
Completed 1997 |
| Central Plant Building (X) |
|
Completed 1995 |
Completed 1995 |
Completed 1995 |
| Schnell Hall (history/poly sci) - Remodel |
|
Completed 1998 - demolished and replaced with Colt Hall |
Completed 1998 - demolished and replaced with Colt Hall |
Completed 1998 - demolished and replaced with Colt Hall |
| Wood Hall Remodel (psych/sociology) |
|
Completed 1997 - renamed Culbertson Hall |
Completed 1997 - renamed Culbertson Hall |
Completed 1997 - renamed Culbertson Hall |
| Rohr Science 2nd floor remodel (Math/CS) |
|
|
|
Completed 2004 - done in phases |
| Evans Hall Remodel (HES/Teacher Ed) |
|
|
Completed 1999 |
Completed 1999 |
| Cafeteria remodel (7) (Lit/Lang) |
|
|
|
Completed 1999 - named Bond Academic Center |
| Rohr North (Business) remodel |
|
|
|
2004 - This half of the building demolished to clear space for Fermanian School of Business building |
| Taylor Hall Remodel (Nursing) |
|
|
|
Completed 2001 |
| PLEI Program Relocation |
|
|
Program no longer in existence |
Program no longer in existence |
| Hillside Mitigation |
|
|
|
|
| Campus Entrance Renovation |
|
|
|
Completed 2001 |
| Wesley Center Space created in the Ryan Library |
|
|
Completed 1998 |
Completed 1998 |
| Demolition of Student Services Building |
|
|
|
Completed 2003 |
| Removal of Starkey Trailer |
|
1994 (approximate date) |
1994 (approximate date) |
1994 (approximate date) |
| Demolition of Post Office Building |
|
|
Demolished 1994 |
Demolished 1994 |
| Demolition of Bookstore Building |
|
|
Demolished 1994 |
Demolished 1994 |
| Campus wide Telecommunications Infrastructure |
|
|
Completed 1998 |
Completed 1998 |
| Gym Parking Lot modifications |
|
|
|
Completed Late 1999 |
| Gym Parking Lot (10) |
|
|
|
|
| North Campus parking facility (3) |
|
|
|
|
| North Campus parking lot |
|
|
|
Reconfigured to split level Completed 2004 |
| East Campus Parking Facility (12) |
|
|
|
Completed 1999 |
| Nease dorm addition (2) |
|
|
|
Completed 2004 |
| Goodwin dorm addition (1) |
|
|
|
|
| Administrative Building (4) |
|
|
|
Completed 2005 - named Draper Hall |
| McAlpin House |
|
|
|
Demolition for Draper Hall 2003 |
| Bleachers (13) |
|
|
|
|
| Small Fitness Center |
Completed 1994 |
Completed 1994 |
Completed 1994 |
Completed 1994 |
| Fitness Center extension of the gym (9) |
|
|
|
|
| Starkey B Remodel (Early Childhood Center) |
|
Completed 1996 |
Completed 1996 |
Completed 1996 |
| Campus Services (8) (Physical Plant) |
|
|
|
Completed 2002 - Remodel and addition rather than new building |
| Remodel Rohr Science as part of the Science Complex |
|
|
1999 added to campus priorities |
|
| New Science Building as part of the Science Complex |
|
|
1999 added to campus priorities |
|
| Fermanian School of Business building and parking |
|
|
1999 added to campus priorities |
Completed 2005 |
| Softball field over Young parking lot |
|
|
1999 added to campus priorities |
|
| New Building for the School of Theology and the Center for Pastoral Leadership |
|
|
|
2005 added to campus priorities by the Board. |
Note: The numbers in ( ) are linked to the December 19, 1995 campus plan.
Note: The projects highlighted in gray are open.